Every off-plan project in Dubai, and how far along it really is
Official construction progress for 1,429 projects registered with the Dubai Land Department, with each project's planned completion date and a clock counting down to it, or up from it when it has passed.
1,209projects under construction
324,705homes and units in them
250past their planned completion date
220registered, not started yet
Launching soon and just launched
Sales launches and EOI openings with a sourced date, from Homes.me's launch clock. A date no developer has confirmed says "Best guess".
Talay & Talay Beach Saadiyat, Abu Dhabi Launched Sep 23, 2026 Sep 23, 2026
Yas Riva Reserve Yas Island, Abu Dhabi Launched Sep 26, 2026 Sep 26, 2026
Wadeem Gardens by Modon Hudayriyat Island, Abu Dhabi Launched Sep 30, 2026 Sep 30, 2026
Nad Al Sheba Gardens Phase 12 Nad Al Sheba, Dubai Sales launch Nov 13, 2026Best guess Nov 13, 2026
Kore by Imtiaz Dubailand, Dubai Sales launch Nov 15, 2026Best guess Nov 15, 2026
Palm Springs Jebel Ali, Dubai EOI opens Nov 2026Best guess Nov 2026
- Lyra at Ghaf Woods Ghaf Woods, Dubai Sales launch Nov 2026Best guess Nov 2026
Progress reported most recently
Projects whose official progress went up at the latest update of the register.
- Binghatti Amberhall Jumeirah Village Circle · Binghatti 70.01%Planned Feb 28, 2026, 8 months ago
- Violet Tower Jumeirah Village Circle · Dubai Investment Real Estate 90.15%Planned Jun 30, 2026, 4 months ago
- Vincitore Dolce Vita Arjan · Vincitore 40%No planned date in the register
- Haven by Aldar 1 Wadi Al Safa 5 · Aurora Spv 1 61.03%Planned completion Nov 28, 2027
- Uh East by Ellington DMCC Master Community · Ellington 62.75%Planned Mar 30, 2026, 7 months ago
- Haven by Aldar 2 Wadi Al Safa 5 · Aurora Spv 1 53.41%No planned date in the register
- The Waterside Villas by Ellington Mohammed Bin Rashid Al Maktoum District 11 · Ellington 45.04%Planned Jun 30, 2026, 4 months ago
- Naya at District One Mohammed Bin Rashid Al Maktoum City -District -1 Community · District One - FZ 68.45%Planned completion Sep 30, 2027
Past their planned completion this year
Under construction, with the planned completion date in the register passed within the last 12 months. All 250 past their date
- Azizi Venice 14 Dubai World Central · Azizi 30.29%Planned May 30, 2026, 5 months ago
- Azizi Venice 7 Dubai World Central · Azizi 29.19%Planned Jan 28, 2026, 9 months ago
- Binghatti Elite International Media Production Zone · Binghatti 53.25%Planned Jun 30, 2026, 4 months ago
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Binghatti Hillviews Dubai Science Park · Binghatti 32.6%Planned Apr 1, 2026, 7 months ago
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- One by Binghatti Business Bay · Binghatti 50.21%Planned May 30, 2026, 5 months ago
- Lime Light Twin Towers Dubai Sports City · Lime Light Real Estate Development 71.09%Planned Jun 30, 2026, 4 months ago
The largest projects under construction
- Azizi Venice 14 Dubai World Central · Azizi 30.29%Planned May 30, 2026, 5 months ago
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Sobha One Ras Al Khor Industrial First · Sobha 86.21%No planned date in the register
- Sobha Orbis Motor City · Sobha 18.2%Planned completion Dec 31, 2028
- Azizi Venice 6 Dubai World Central · Azizi 11.58%Planned completion Dec 31, 2027
- Skyvue Bukadra · Sobha 10.54%Planned completion Mar 31, 2030
- Sobha Central Phase I DMCC-EZ2 · Sobha 7.08%Planned completion Jun 30, 2030
- Sobha Solis Motor City · Sobha 17.92%Planned completion Dec 31, 2028